1. Network diagram : Activity, Predecessors example ( Enter your problem )
  1. Example-1
Other related methods
  1. Network diagram : Activity, Predecessors
  2. Network diagram : Activity i-j
  3. Network diagram : Activity i-j, Name of Activity
  4. Critical path, Total float, Free float, Independent float : Activity, Predecessors, Duration
  5. Critical path, Total float, Free float, Independent float : Activity i-j, Duration
  6. Critical path, Total float, Free float, Independent float : Activity i-j, Name of Activity, Duration
  7. Project scheduling : Activity, Predecessors, to, tm, tp
  8. Project scheduling : Activity i-j, to, tm, tp
  9. Project scheduling : Activity i-j, Name of Activity, to, tm, tp
  10. Project crashing : Activity, Predecessors, Normal Time & Cost, Crash Time & Cost and Indirect Cost
  11. Project crashing : Activity i-j, Normal Time & Cost, Crash Time & Cost and Indirect Cost
  12. Project crashing : Activity i-j, Name of Activity, Normal Time & Cost, Crash Time & Cost and Indirect Cost
  13. Project crashing : Activity, Predecessors, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost
  14. Project crashing : Activity i-j, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost
  15. Project crashing : Activity i-j, Name of Activity, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost

2. Network diagram : Activity i-j
(Next method)

1. Example-1





Draw Network diagram
A-
BA
CA
DB
EB,C
FE
GD,F
HG


Solution:
ActivityImmediate Predecessors
A-
BA
CA
DB
EB,C
FE
GD,F
HG


Edge and it's preceded and succeeded node
EdgeNode1 `->` Node2
A1`->`2
B2`->`3
C2`->`4
d3`->`4
D3`->`6
E4`->`5
F5`->`6
G6`->`7
H7`->`8



The network diagram for the project is
 B `B : 2->3`
3
 D `D : 3->6`
6
 G `G : 6->7`
7
 H `H : 7->8`
8
1
 A `A : 1->2`
2
 d `d : 3->4`
 F `F : 5->6`
 C `C : 2->4`
4
 E `E : 4->5`
5



This material is intended as a summary. Use your textbook for detail explanation.
Any bug, improvement, feedback then Submit Here



2. Network diagram : Activity i-j
(Next method)





Share this solution or page with your friends.


 
Copyright © 2023. All rights reserved. Terms, Privacy
 
 

.