1. An assembly is to be made from two parts X and Y. Both parts must be turned on a lathe
Y must be polished where as X need not be polished. The sequence of acitivities, together with their
predecessors, is given below
Activity |
Description |
Predecessor Activity |
A |
Open work order |
- |
B |
Get material for X |
A |
C |
Get material for Y |
A |
D |
Turn X on lathe |
B |
E |
Turn Y on lathe |
B,C |
F |
Polish Y |
E |
G |
Assemble X and Y |
D,F |
H |
Pack |
G |
Draw a network diagram of activities for the project.
2. An established company has decided to add a new product to its line. It will buy the
product from a manufacturing concern, package it, and sell it to a number of distributors that have been
selected on a geographical basis. Market research has already indicated the volume expected and the size
of sales force required. The steps shown in the following table are to be planned.
Activity |
Description |
Predecessor Activity |
Duration (days) |
A |
|
- |
14 |
B |
|
A |
4 |
C |
|
B |
2 |
D |
|
C |
1 |
E |
|
A |
2 |
F |
|
E |
3 |
G |
|
E |
2 |
H |
|
E |
4 |
I |
|
H,L |
3 |
J |
|
K |
12 |
K |
|
D,F,G |
4 |
L |
|
J |
2 |
M |
|
H,L |
2 |
(a) Draw an arrow diagram for the project.
(b) Indicate the criticla path.
(c) For each non-critical activity, find the total and free float.
|
|
|
|
|
|