Home > Operation Research calculators > Critical path, Total float, Free float, Independent float calculator

Algorithm and examples
PERT and CPM
Critical path, Total float, Free float, Independent float
Type your data, for seperator you can use space or tab
OR
Rows :
Activity i-jDuration


Code is improved for all kind of Input.
Note: If you get error message for any method (AON/AOA) then try with other method to get solution and also submit the feedback form
So, I will try my best to improve it soon.
SolutionHelp
Critical path, Total float, Free float, Independent float calculator
1. An assembly is to be made from two parts X and Y. Both parts must be turned on a lathe Y must be polished where as X need not be polished. The sequence of acitivities, together with their predecessors, is given below
Activity Description Predecessor Activity
A Open work order -
B Get material for X A
C Get material for Y A
D Turn X on lathe B
E Turn Y on lathe B,C
F Polish Y E
G Assemble X and Y D,F
H Pack G
Draw a network diagram of activities for the project.


2. An established company has decided to add a new product to its line. It will buy the product from a manufacturing concern, package it, and sell it to a number of distributors that have been selected on a geographical basis. Market research has already indicated the volume expected and the size of sales force required. The steps shown in the following table are to be planned.
Activity Description Predecessor Activity Duration (days)
A - 14
B A 4
C B 2
D C 1
E A 2
F E 3
G E 2
H E 4
I H,L 3
J K 12
K D,F,G 4
L J 2
M H,L 2
(a) Draw an arrow diagram for the project.
(b) Indicate the criticla path.
(c) For each non-critical activity, find the total and free float.