        | Project crashing to solve Time-Cost Trade-Off with varying Indirect cost calculator |  
        |  1. An assembly is to be made from two parts X and Y. Both parts must be turned on a lathe
	Y must be polished where as X need not be polished. The sequence of acitivities, together with their 
	predecessors, is given below 
        Draw a network diagram of activities for the project.
            | Activity | Description | Predecessor Activity |  
            | A | Open work order | - |  
            | B | Get material for X | A |  
            | C | Get material for Y | A |  
            | D | Turn X on lathe | B |  
            | E | Turn Y on lathe | B,C |  
            | F | Polish Y | E |  
            | G | Assemble X and Y | D,F |  
            | H | Pack | G |  
 
 
  2. An established company has decided to add a new product to its line. It will buy the
	product from a manufacturing concern, package it, and sell it to a number of distributors that have been 
	selected on a geographical basis. Market research has already indicated the volume expected and the size 
	of sales force required. The steps shown in the following table are to be planned. 
        (a) Draw an arrow diagram for the project.
            | Activity | Description | Predecessor Activity | Duration (days) |  
            | A |  | - | 14 |  
            | B |  | A | 4 |  
            | C |  | B | 2 |  
            | D |  | C | 1 |  
            | E |  | A | 2 |  
            | F |  | E | 3 |  
            | G |  | E | 2 |  
            | H |  | E | 4 |  
            | I |  | H,L | 3 |  
            | J |  | K | 12 |  
            | K |  | D,F,G | 4 |  
            | L |  | J | 2 |  
            | M |  | H,L | 2 |  (b) Indicate the criticla path.
 (c) For each non-critical activity, find the total and free float.
 
 |  |  
            |  |  
            |  |  |  |