Project crashing to solve Time-Cost Trade-Off with varying Indirect cost
| 1-2 | 4 | 60 | 3 | 90 |
| 1-4 | 6 | 150 | 4 | 250 |
| 1-3 | 2 | 38 | 1 | 60 |
| 2-4 | 5 | 150 | 3 | 250 |
| 3-4 | 2 | 100 | 2 | 100 |
| 2-5 | 7 | 115 | 5 | 175 |
| 4-5 | 4 | 100 | 2 | 240 |
Varying Indirect cost
Month = 15,14,13,12,11,10,9,8,7,6
Cost = 600,500,400,250,175,100,75,50,35,25Solution:The given problem is
| Activity | Name | Normal Time | Normal Cost | Crash Time | Crash Cost |
| 1-2 | A0 | 4 | 60 | 3 | 90 |
| 1-4 | A1 | 6 | 150 | 4 | 250 |
| 1-3 | A2 | 2 | 38 | 1 | 60 |
| 2-4 | A3 | 5 | 150 | 3 | 250 |
| 3-4 | A4 | 2 | 100 | 2 | 100 |
| 2-5 | A5 | 7 | 115 | 5 | 175 |
| 4-5 | A6 | 4 | 100 | 2 | 240 |
Edge and it's preceded and succeeded node
| Edge | Node1 `->` Node2 |
| A0 | 1`->`2 |
| A2 | 1`->`3 |
| A1 | 1`->`4 |
| A3 | 2`->`4 |
| A5 | 2`->`5 |
| A4 | 3`->`4 |
| A6 | 4`->`5 |
The network diagram for the project, along with activity time, is
(Note: Same diagram as above. Move node position by dragging node.
If you are not able to select node then just click here for
)
Forward Pass Method
Forward Pass Method
`E_1=0`
`E_2=E_1 + t_(1,2)``=0 + 4``=4`
`E_3=E_1 + t_(1,3)``=0 + 2``=2`
`E_4=Max{E_i + t_(i,4)} [i=1, 2, 3]`
`=Max{E_1 + t_(1,4); E_2 + t_(2,4); E_3 + t_(3,4)}`
`=Max{0 + 6; 4 + 5; 2 + 2}`
`=Max{6; 9; 4}`
`=9`
`E_5=Max{E_i + t_(i,5)} [i=2, 4]`
`=Max{E_2 + t_(2,5); E_4 + t_(4,5)}`
`=Max{4 + 7; 9 + 4}`
`=Max{11; 13}`
`=13`
Backward Pass Method
Backward Pass Method
`L_5=E_5=13`
`L_4=L_5 - t_(4,5)``=13 - 4``=9`
`L_3=L_4 - t_(3,4)``=9 - 2``=7`
`L_2=text{Min}{L_j - t_(2,j)} [j=4, 5]`
`=text{Min}{L_4 - t_(2,4); L_5 - t_(2,5)}`
`=text{Min}{9 - 5; 13 - 7}`
`=text{Min}{4; 6}`
`=4`
`L_1=text{Min}{L_j - t_(1,j)} [j=2, 3, 4]`
`=text{Min}{L_2 - t_(1,2); L_3 - t_(1,3); L_4 - t_(1,4)}`
`=text{Min}{4 - 4; 7 - 2; 9 - 6}`
`=text{Min}{0; 5; 3}`
`=0`
(b) The critical path in the network diagram has been shown. This has been done by red lines by joining all those events where E-values and L-values are equal.
The critical path of the project is : `1-2-4-5` and critical activities are `A0,A3,A6`
The total project time is 13
The network diagram for the project, along with E-values and L-values, is
(Note: Same diagram as above. Move node position by dragging node.
If you are not able to select node then just click here for
)
The crash cost slope for various activities is
| Critical activity | Crash cost per week (Rs) |
| A0 (1 - 2) | `(90-60)/(4-3)=30` |
| A2 (1 - 3) | `(60-38)/(2-1)=22` |
| A1 (1 - 4) | `(250-150)/(6-4)=50` |
| A3 (2 - 4) | `(250-150)/(5-3)=50` |
| A5 (2 - 5) | `(175-115)/(7-5)=30` |
| A4 (3 - 4) | - |
| A6 (4 - 5) | `(240-100)/(4-2)=70` |
Total cost = Direct normal cost + Indirect cost for 13 weeks
`=713+400=1113`
`1^(st)` Crashing :The critical activity A0 with cost slope of Rs 30 per week, is the least expensive and can be crashed by 1 weeks
E-values and L-values for next crashed network
Forward Pass Method
Forward Pass Method
`E_1=0`
`E_2=E_1 + t_(1,2)``=0 + 3``=3`
`E_3=E_1 + t_(1,3)``=0 + 2``=2`
`E_4=Max{E_i + t_(i,4)} [i=1, 2, 3]`
`=Max{E_1 + t_(1,4); E_2 + t_(2,4); E_3 + t_(3,4)}`
`=Max{0 + 6; 3 + 5; 2 + 2}`
`=Max{6; 8; 4}`
`=8`
`E_5=Max{E_i + t_(i,5)} [i=2, 4]`
`=Max{E_2 + t_(2,5); E_4 + t_(4,5)}`
`=Max{3 + 7; 8 + 4}`
`=Max{10; 12}`
`=12`
Backward Pass Method
Backward Pass Method
`L_5=E_5=12`
`L_4=L_5 - t_(4,5)``=12 - 4``=8`
`L_3=L_4 - t_(3,4)``=8 - 2``=6`
`L_2=text{Min}{L_j - t_(2,j)} [j=4, 5]`
`=text{Min}{L_4 - t_(2,4); L_5 - t_(2,5)}`
`=text{Min}{8 - 5; 12 - 7}`
`=text{Min}{3; 5}`
`=3`
`L_1=text{Min}{L_j - t_(1,j)} [j=2, 3, 4]`
`=text{Min}{L_2 - t_(1,2); L_3 - t_(1,3); L_4 - t_(1,4)}`
`=text{Min}{3 - 3; 6 - 2; 8 - 6}`
`=text{Min}{0; 4; 2}`
`=0`
(b) The critical path in the network diagram has been shown. This has been done by red lines by joining all those events where E-values and L-values are equal.
The critical path of the project is : `1-2-4-5` and critical activities are `A0,A3,A6`
The total project time is 12
The network diagram for the project, along with E-values and L-values, is
(Note: Same diagram as above. Move node position by dragging node.
If you are not able to select node then just click here for
)
Total cost = Direct normal cost + Indirect cost for 12 weeks
`=713+1xx30+250=993`
`2^(nd)` Crashing :The critical activity A3 with cost slope of Rs 50 per week, is the least expensive and can be crashed by 2 weeks
E-values and L-values for next crashed network
Forward Pass Method
Forward Pass Method
`E_1=0`
`E_2=E_1 + t_(1,2)``=0 + 3``=3`
`E_3=E_1 + t_(1,3)``=0 + 2``=2`
`E_4=Max{E_i + t_(i,4)} [i=1, 2, 3]`
`=Max{E_1 + t_(1,4); E_2 + t_(2,4); E_3 + t_(3,4)}`
`=Max{0 + 6; 3 + 3; 2 + 2}`
`=Max{6; 6; 4}`
`=6`
`E_5=Max{E_i + t_(i,5)} [i=2, 4]`
`=Max{E_2 + t_(2,5); E_4 + t_(4,5)}`
`=Max{3 + 7; 6 + 4}`
`=Max{10; 10}`
`=10`
Backward Pass Method
Backward Pass Method
`L_5=E_5=10`
`L_4=L_5 - t_(4,5)``=10 - 4``=6`
`L_3=L_4 - t_(3,4)``=6 - 2``=4`
`L_2=text{Min}{L_j - t_(2,j)} [j=4, 5]`
`=text{Min}{L_4 - t_(2,4); L_5 - t_(2,5)}`
`=text{Min}{6 - 3; 10 - 7}`
`=text{Min}{3; 3}`
`=3`
`L_1=text{Min}{L_j - t_(1,j)} [j=2, 3, 4]`
`=text{Min}{L_2 - t_(1,2); L_3 - t_(1,3); L_4 - t_(1,4)}`
`=text{Min}{3 - 3; 4 - 2; 6 - 6}`
`=text{Min}{0; 2; 0}`
`=0`
(b) The critical path in the network diagram has been shown. This has been done by red lines by joining all those events where E-values and L-values are equal.
The critical path of the project are :
(1) `1-2-4-5` and critical activities : `A0,A3,A6`
(2) `1-2-5` and critical activities : `A0,A5`
(3) `1-4-5` and critical activities : `A1,A6`
The total project time is 10
The network diagram for the project, along with E-values and L-values, is
(Note: Same diagram as above. Move node position by dragging node.
If you are not able to select node then just click here for
)
Total cost = Direct normal cost + Indirect cost for 10 weeks
`=713+30+2xx50+100=943`
`3^(rd)` Crashing :The crashing activity `A6` in the path `1-2-4-5` `(A0,A3,A6)`, activity `A5` in the path `1-2-5` `(A0,A5)`, each by 2 week
E-values and L-values for next crashed network
Forward Pass Method
Forward Pass Method
`E_1=0`
`E_2=E_1 + t_(1,2)``=0 + 3``=3`
`E_3=E_1 + t_(1,3)``=0 + 2``=2`
`E_4=Max{E_i + t_(i,4)} [i=1, 2, 3]`
`=Max{E_1 + t_(1,4); E_2 + t_(2,4); E_3 + t_(3,4)}`
`=Max{0 + 6; 3 + 3; 2 + 2}`
`=Max{6; 6; 4}`
`=6`
`E_5=Max{E_i + t_(i,5)} [i=2, 4]`
`=Max{E_2 + t_(2,5); E_4 + t_(4,5)}`
`=Max{3 + 5; 6 + 2}`
`=Max{8; 8}`
`=8`
Backward Pass Method
Backward Pass Method
`L_5=E_5=8`
`L_4=L_5 - t_(4,5)``=8 - 2``=6`
`L_3=L_4 - t_(3,4)``=6 - 2``=4`
`L_2=text{Min}{L_j - t_(2,j)} [j=4, 5]`
`=text{Min}{L_4 - t_(2,4); L_5 - t_(2,5)}`
`=text{Min}{6 - 3; 8 - 5}`
`=text{Min}{3; 3}`
`=3`
`L_1=text{Min}{L_j - t_(1,j)} [j=2, 3, 4]`
`=text{Min}{L_2 - t_(1,2); L_3 - t_(1,3); L_4 - t_(1,4)}`
`=text{Min}{3 - 3; 4 - 2; 6 - 6}`
`=text{Min}{0; 2; 0}`
`=0`
(b) The critical path in the network diagram has been shown. This has been done by red lines by joining all those events where E-values and L-values are equal.
The critical path of the project are :
(1) `1-2-4-5` and critical activities : `A0,A3,A6`
(2) `1-2-5` and critical activities : `A0,A5`
(3) `1-4-5` and critical activities : `A1,A6`
The total project time is 8
The network diagram for the project, along with E-values and L-values, is
(Note: Same diagram as above. Move node position by dragging node.
If you are not able to select node then just click here for
)
Total cost = Direct normal cost + Indirect cost for 8 weeks
`=713+130+2xx30+2xx70+50=1093`
Since total project cost for 8 weeks is more than the cost for 10 weeks. So further crashing is not desirable.
Hence, project optimum time is 10 weeks and cost is 943.
Crashing schedule of project
Project duration | Crashing activity and time | Direct Normal Cost | Direct Crashing Cost | Total (Normal + Crashing) | Indirect Cost | Total Cost |
| 13 | | 713 | `` | 713 | `400` | 1113 |
| 12 | A0=1 | 713 | `1xx30=30` | 743 | `250` | 993 |
| 10 | A3=2 | 713 | `30+2xx50=130` | 843 | `100` | 943 |
| 8 | A5;A6=2 | 713 | `130+2xx30+2xx70=330` | 1043 | `50` | 1093 |
This material is intended as a summary. Use your textbook for detail explanation.
Any bug, improvement, feedback then