Home > Operation Research calculators > Project crashing to solve Time-Cost Trade-Off with varying Indirect cost example

14. Project crashing : Activity i-j, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost example ( Enter your problem )
  1. Example-1
Other related methods
  1. Network diagram : Activity, Predecessors
  2. Network diagram : Activity i-j
  3. Network diagram : Activity i-j, Name of Activity
  4. Critical path, Total float, Free float, Independent float : Activity, Predecessors, Duration
  5. Critical path, Total float, Free float, Independent float : Activity i-j, Duration
  6. Critical path, Total float, Free float, Independent float : Activity i-j, Name of Activity, Duration
  7. Project scheduling : Activity, Predecessors, to, tm, tp
  8. Project scheduling : Activity i-j, to, tm, tp
  9. Project scheduling : Activity i-j, Name of Activity, to, tm, tp
  10. Project crashing : Activity, Predecessors, Normal Time & Cost, Crash Time & Cost and Indirect Cost
  11. Project crashing : Activity i-j, Normal Time & Cost, Crash Time & Cost and Indirect Cost
  12. Project crashing : Activity i-j, Name of Activity, Normal Time & Cost, Crash Time & Cost and Indirect Cost
  13. Project crashing : Activity, Predecessors, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost
  14. Project crashing : Activity i-j, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost
  15. Project crashing : Activity i-j, Name of Activity, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost

13. Project crashing : Activity, Predecessors, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost
(Previous method)
15. Project crashing : Activity i-j, Name of Activity, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost
(Next method)

1. Example-1





Project crashing to solve Time-Cost Trade-Off with varying Indirect cost
1-2460390
1-461504250
1-3238160
2-451503250
3-421002100
2-571155175
4-541002240

Varying Indirect cost
Month = 15,14,13,12,11,10,9,8,7,6
Cost = 600,500,400,250,175,100,75,50,35,25


Solution:
The given problem is
ActivityNameNormal
Time
Normal
Cost
Crash
Time
Crash
Cost
1-2A0460390
1-4A161504250
1-3A2238160
2-4A351503250
3-4A421002100
2-5A571155175
4-5A641002240


Edge and it's preceded and succeeded node
EdgeNode1 `->` Node2
A01`->`2
A21`->`3
A11`->`4
A32`->`4
A52`->`5
A43`->`4
A64`->`5



The network diagram for the project, along with activity time, is
2
A0(4)
A3(5)
A5(7)
1
A2(2)
A3(5)
3
5
A1(6)
A3(5)
A4(2)
A6(4)
4

(Note: Same diagram as above. Move node position by dragging node.
If you are not able to select node then just click here for )
not supported


Forward Pass Method

Forward Pass Method

`E_1=0`

`E_2=E_1 + t_(1,2)``=0 + 4``=4`

`E_3=E_1 + t_(1,3)``=0 + 2``=2`

`E_4=Max{E_i + t_(i,4)} [i=1, 2, 3]`

`=Max{E_1 + t_(1,4); E_2 + t_(2,4); E_3 + t_(3,4)}`

`=Max{0 + 6; 4 + 5; 2 + 2}`

`=Max{6; 9; 4}`

`=9`

`E_5=Max{E_i + t_(i,5)} [i=2, 4]`

`=Max{E_2 + t_(2,5); E_4 + t_(4,5)}`

`=Max{4 + 7; 9 + 4}`

`=Max{11; 13}`

`=13`


Backward Pass Method

Backward Pass Method

`L_5=E_5=13`

`L_4=L_5 - t_(4,5)``=13 - 4``=9`

`L_3=L_4 - t_(3,4)``=9 - 2``=7`

`L_2=text{Min}{L_j - t_(2,j)} [j=4, 5]`

`=text{Min}{L_4 - t_(2,4); L_5 - t_(2,5)}`

`=text{Min}{9 - 5; 13 - 7}`

`=text{Min}{4; 6}`

`=4`

`L_1=text{Min}{L_j - t_(1,j)} [j=2, 3, 4]`

`=text{Min}{L_2 - t_(1,2); L_3 - t_(1,3); L_4 - t_(1,4)}`

`=text{Min}{4 - 4; 7 - 2; 9 - 6}`

`=text{Min}{0; 5; 3}`

`=0`


(b) The critical path in the network diagram has been shown. This has been done by red lines by joining all those events where E-values and L-values are equal.
The critical path of the project is : `1-2-4-5` and critical activities are `A0,A3,A6`

The total project time is 13
The network diagram for the project, along with E-values and L-values, is
`E_(2)=4`
`L_(2)=4`
2
A0(4)
A3(5)
A5(7)
1
A2(2)
A3(5)
3
`E_(3)=2`
`L_(3)=7`
5
`E_(1)=0`
`L_(1)=0`
A1(6)
A3(5)
A4(2)
A6(4)
`E_(5)=13`
`L_(5)=13`
`E_(4)=9`
`L_(4)=9`
4


(Note: Same diagram as above. Move node position by dragging node.
If you are not able to select node then just click here for )
not supported


The crash cost slope for various activities is
Critical activityCrash cost per week (Rs)
A0 (1 - 2)`(90-60)/(4-3)=30`
A2 (1 - 3)`(60-38)/(2-1)=22`
A1 (1 - 4)`(250-150)/(6-4)=50`
A3 (2 - 4)`(250-150)/(5-3)=50`
A5 (2 - 5)`(175-115)/(7-5)=30`
A4 (3 - 4)-
A6 (4 - 5)`(240-100)/(4-2)=70`



Total cost = Direct normal cost + Indirect cost for 13 weeks
`=713+400=1113`



`1^(st)` Crashing :

The critical activity A0 with cost slope of Rs 30 per week, is the least expensive and can be crashed by 1 weeks

E-values and L-values for next crashed network
Forward Pass Method

Forward Pass Method

`E_1=0`

`E_2=E_1 + t_(1,2)``=0 + 3``=3`

`E_3=E_1 + t_(1,3)``=0 + 2``=2`

`E_4=Max{E_i + t_(i,4)} [i=1, 2, 3]`

`=Max{E_1 + t_(1,4); E_2 + t_(2,4); E_3 + t_(3,4)}`

`=Max{0 + 6; 3 + 5; 2 + 2}`

`=Max{6; 8; 4}`

`=8`

`E_5=Max{E_i + t_(i,5)} [i=2, 4]`

`=Max{E_2 + t_(2,5); E_4 + t_(4,5)}`

`=Max{3 + 7; 8 + 4}`

`=Max{10; 12}`

`=12`


Backward Pass Method

Backward Pass Method

`L_5=E_5=12`

`L_4=L_5 - t_(4,5)``=12 - 4``=8`

`L_3=L_4 - t_(3,4)``=8 - 2``=6`

`L_2=text{Min}{L_j - t_(2,j)} [j=4, 5]`

`=text{Min}{L_4 - t_(2,4); L_5 - t_(2,5)}`

`=text{Min}{8 - 5; 12 - 7}`

`=text{Min}{3; 5}`

`=3`

`L_1=text{Min}{L_j - t_(1,j)} [j=2, 3, 4]`

`=text{Min}{L_2 - t_(1,2); L_3 - t_(1,3); L_4 - t_(1,4)}`

`=text{Min}{3 - 3; 6 - 2; 8 - 6}`

`=text{Min}{0; 4; 2}`

`=0`


(b) The critical path in the network diagram has been shown. This has been done by red lines by joining all those events where E-values and L-values are equal.
The critical path of the project is : `1-2-4-5` and critical activities are `A0,A3,A6`

The total project time is 12
The network diagram for the project, along with E-values and L-values, is
`E_(2)=3`
`L_(2)=3`
2
A0(3)
A3(5)
A5(7)
1
A2(2)
A3(5)
3
`E_(3)=2`
`L_(3)=6`
5
`E_(1)=0`
`L_(1)=0`
A1(6)
A3(5)
A4(2)
A6(4)
`E_(5)=12`
`L_(5)=12`
`E_(4)=8`
`L_(4)=8`
4


(Note: Same diagram as above. Move node position by dragging node.
If you are not able to select node then just click here for )
not supported


Total cost = Direct normal cost + Indirect cost for 12 weeks
`=713+1xx30+250=993`



`2^(nd)` Crashing :

The critical activity A3 with cost slope of Rs 50 per week, is the least expensive and can be crashed by 2 weeks

E-values and L-values for next crashed network
Forward Pass Method

Forward Pass Method

`E_1=0`

`E_2=E_1 + t_(1,2)``=0 + 3``=3`

`E_3=E_1 + t_(1,3)``=0 + 2``=2`

`E_4=Max{E_i + t_(i,4)} [i=1, 2, 3]`

`=Max{E_1 + t_(1,4); E_2 + t_(2,4); E_3 + t_(3,4)}`

`=Max{0 + 6; 3 + 3; 2 + 2}`

`=Max{6; 6; 4}`

`=6`

`E_5=Max{E_i + t_(i,5)} [i=2, 4]`

`=Max{E_2 + t_(2,5); E_4 + t_(4,5)}`

`=Max{3 + 7; 6 + 4}`

`=Max{10; 10}`

`=10`


Backward Pass Method

Backward Pass Method

`L_5=E_5=10`

`L_4=L_5 - t_(4,5)``=10 - 4``=6`

`L_3=L_4 - t_(3,4)``=6 - 2``=4`

`L_2=text{Min}{L_j - t_(2,j)} [j=4, 5]`

`=text{Min}{L_4 - t_(2,4); L_5 - t_(2,5)}`

`=text{Min}{6 - 3; 10 - 7}`

`=text{Min}{3; 3}`

`=3`

`L_1=text{Min}{L_j - t_(1,j)} [j=2, 3, 4]`

`=text{Min}{L_2 - t_(1,2); L_3 - t_(1,3); L_4 - t_(1,4)}`

`=text{Min}{3 - 3; 4 - 2; 6 - 6}`

`=text{Min}{0; 2; 0}`

`=0`


(b) The critical path in the network diagram has been shown. This has been done by red lines by joining all those events where E-values and L-values are equal.
The critical path of the project are :
(1) `1-2-4-5` and critical activities : `A0,A3,A6`

(2) `1-2-5` and critical activities : `A0,A5`

(3) `1-4-5` and critical activities : `A1,A6`

The total project time is 10
The network diagram for the project, along with E-values and L-values, is
`E_(2)=3`
`L_(2)=3`
2
A0(3)
A3(3)
A5(7)
1
A2(2)
A3(3)
3
`E_(3)=2`
`L_(3)=4`
5
`E_(1)=0`
`L_(1)=0`
A1(6)
A3(3)
A4(2)
A6(4)
`E_(5)=10`
`L_(5)=10`
`E_(4)=6`
`L_(4)=6`
4


(Note: Same diagram as above. Move node position by dragging node.
If you are not able to select node then just click here for )
not supported


Total cost = Direct normal cost + Indirect cost for 10 weeks
`=713+30+2xx50+100=943`



`3^(rd)` Crashing :

The crashing activity `A6` in the path `1-2-4-5` `(A0,A3,A6)`, activity `A5` in the path `1-2-5` `(A0,A5)`, each by 2 week


E-values and L-values for next crashed network
Forward Pass Method

Forward Pass Method

`E_1=0`

`E_2=E_1 + t_(1,2)``=0 + 3``=3`

`E_3=E_1 + t_(1,3)``=0 + 2``=2`

`E_4=Max{E_i + t_(i,4)} [i=1, 2, 3]`

`=Max{E_1 + t_(1,4); E_2 + t_(2,4); E_3 + t_(3,4)}`

`=Max{0 + 6; 3 + 3; 2 + 2}`

`=Max{6; 6; 4}`

`=6`

`E_5=Max{E_i + t_(i,5)} [i=2, 4]`

`=Max{E_2 + t_(2,5); E_4 + t_(4,5)}`

`=Max{3 + 5; 6 + 2}`

`=Max{8; 8}`

`=8`


Backward Pass Method

Backward Pass Method

`L_5=E_5=8`

`L_4=L_5 - t_(4,5)``=8 - 2``=6`

`L_3=L_4 - t_(3,4)``=6 - 2``=4`

`L_2=text{Min}{L_j - t_(2,j)} [j=4, 5]`

`=text{Min}{L_4 - t_(2,4); L_5 - t_(2,5)}`

`=text{Min}{6 - 3; 8 - 5}`

`=text{Min}{3; 3}`

`=3`

`L_1=text{Min}{L_j - t_(1,j)} [j=2, 3, 4]`

`=text{Min}{L_2 - t_(1,2); L_3 - t_(1,3); L_4 - t_(1,4)}`

`=text{Min}{3 - 3; 4 - 2; 6 - 6}`

`=text{Min}{0; 2; 0}`

`=0`


(b) The critical path in the network diagram has been shown. This has been done by red lines by joining all those events where E-values and L-values are equal.
The critical path of the project are :
(1) `1-2-4-5` and critical activities : `A0,A3,A6`

(2) `1-2-5` and critical activities : `A0,A5`

(3) `1-4-5` and critical activities : `A1,A6`

The total project time is 8
The network diagram for the project, along with E-values and L-values, is
`E_(2)=3`
`L_(2)=3`
2
A0(3)
A3(3)
A5(5)
1
A2(2)
A3(3)
3
`E_(3)=2`
`L_(3)=4`
5
`E_(1)=0`
`L_(1)=0`
A1(6)
A3(3)
A4(2)
A6(2)
`E_(5)=8`
`L_(5)=8`
`E_(4)=6`
`L_(4)=6`
4


(Note: Same diagram as above. Move node position by dragging node.
If you are not able to select node then just click here for )
not supported


Total cost = Direct normal cost + Indirect cost for 8 weeks
`=713+130+2xx30+2xx70+50=1093`

Since total project cost for 8 weeks is more than the cost for 10 weeks. So further crashing is not desirable.
Hence, project optimum time is 10 weeks and cost is 943.

Crashing schedule of project
Project
duration
Crashing activity
and time
Direct
Normal Cost
Direct
Crashing Cost
Total
(Normal + Crashing)
Indirect
Cost
Total
Cost
13713``713`400`1113
12A0=1713`1xx30=30`743`250`993
10A3=2713`30+2xx50=130`843`100`943
8A5;A6=2713`130+2xx30+2xx70=330`1043`50`1093





This material is intended as a summary. Use your textbook for detail explanation.
Any bug, improvement, feedback then Submit Here



13. Project crashing : Activity, Predecessors, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost
(Previous method)
15. Project crashing : Activity i-j, Name of Activity, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost
(Next method)





Share this solution or page with your friends.
 
 
Copyright © 2025. All rights reserved. Terms, Privacy
 
 

.