1. Project crashing to solve Time-Cost Trade-Off with varying Indirect cost
| A | - | 4 | 60 | 3 | 90 |
| B | - | 6 | 150 | 4 | 250 |
| C | - | 2 | 38 | 1 | 60 |
| D | A | 5 | 150 | 3 | 250 |
| E | C | 2 | 100 | 2 | 100 |
| F | A | 7 | 115 | 5 | 175 |
| G | D,B,E | 4 | 100 | 2 | 240 |
Varying Indirect cost
Month = 15,14,13,12,11,10,9,8,7,6
Cost = 600,500,400,250,175,100,75,50,35,25Solution:The given problem is
| Activity | Immediate Predecessors | Normal Time | Normal Cost | Crash Time | Crash Cost |
| A | - | 4 | 60 | 3 | 90 |
| B | - | 6 | 150 | 4 | 250 |
| C | - | 2 | 38 | 1 | 60 |
| D | A | 5 | 150 | 3 | 250 |
| E | C | 2 | 100 | 2 | 100 |
| F | A | 7 | 115 | 5 | 175 |
| G | D,B,E | 4 | 100 | 2 | 240 |
Edge and it's preceded and succeeded node
| Edge | Node1 `->` Node2 |
| A | 1`->`2 |
| C | 1`->`3 |
| B | 1`->`4 |
| D | 2`->`4 |
| F | 2`->`5 |
| E | 3`->`4 |
| G | 4`->`5 |
The network diagram for the project, along with activity time, is
| | | | | |
| | | | | |
| | | | | |
| | | D(5) `D : 2->4` | | E(2) `E : 3->4` |
| | | |
| | | | | |
Forward Pass Method
Forward Pass Method
`E_1=0`
`E_2=E_1 + t_(1,2)` [`t_(1,2) = A = 4`]`=0 + 4``=4`
`E_3=E_1 + t_(1,3)` [`t_(1,3) = C = 2`]`=0 + 2``=2`
`E_4=Max{E_i + t_(i,4)} [i=1, 2, 3]`
`=Max{E_1 + t_(1,4); E_2 + t_(2,4); E_3 + t_(3,4)}`
`=Max{0 + 6; 4 + 5; 2 + 2}`
`=Max{6; 9; 4}`
`=9`
`E_5=Max{E_i + t_(i,5)} [i=2, 4]`
`=Max{E_2 + t_(2,5); E_4 + t_(4,5)}`
`=Max{4 + 7; 9 + 4}`
`=Max{11; 13}`
`=13`
Backward Pass Method
Backward Pass Method
`L_5=E_5=13`
`L_4=L_5 - t_(4,5)` [`t_(4,5) = G = 4`]`=13 - 4``=9`
`L_3=L_4 - t_(3,4)` [`t_(3,4) = E = 2`]`=9 - 2``=7`
`L_2=text{Min}{L_j - t_(2,j)} [j=5, 4]`
`=text{Min}{L_5 - t_(2,5); L_4 - t_(2,4)}`
`=text{Min}{13 - 7; 9 - 5}`
`=text{Min}{6; 4}`
`=4`
`L_1=text{Min}{L_j - t_(1,j)} [j=4, 3, 2]`
`=text{Min}{L_4 - t_(1,4); L_3 - t_(1,3); L_2 - t_(1,2)}`
`=text{Min}{9 - 6; 7 - 2; 4 - 4}`
`=text{Min}{3; 5; 0}`
`=0`
(b) The critical path in the network diagram has been shown. This has been done by double lines by joining all those events where E-values and L-values are equal.
The critical path of the project is : `1-2-4-5` and critical activities are `A,D,G`
The total project time is 13
The network diagram for the project, along with E-values and L-values, is
| | | | | |
| | | | | |
| | 3 `E_(3)=2` `L_(3)=7` | | D(5) `D : 2->4` |
| | | |
| | | D(5) `D : 2->4` | | E(2) `E : 3->4` |
| | | |
| | | | | |
| Critical activity | Crash cost per week (Rs) |
| A (1 - 2) | `(90-60)/(4-3)=30` |
| C (1 - 3) | `(60-38)/(2-1)=22` |
| B (1 - 4) | `(250-150)/(6-4)=50` |
| D (2 - 4) | `(250-150)/(5-3)=50` |
| F (2 - 5) | `(175-115)/(7-5)=30` |
| E (3 - 4) | - |
| G (4 - 5) | `(240-100)/(4-2)=70` |
Total cost = Direct normal cost + Indirect cost for 13 weeks
`=713+400=1113`
To begin crash analysis, the crash cost slope values for critical activities is
| Critical activity | Crash cost per week (Rs) |
| A (0 - 1) | `(90-60)/(4-3)=30` |
| D (1 - 3) | `(250-150)/(5-3)=50` |
| G (3 - 4) | `(240-100)/(4-2)=70` |
The critical activity A with cost slope of Rs 30 per week, is the least expensive and can be crashed by 1 weeks
E-values and L-values for next crashed network
Forward Pass Method
Forward Pass Method
`E_1=0`
`E_2=E_1 + t_(1,2)` [`t_(1,2) = A = 3`]`=0 + 3``=3`
`E_3=E_1 + t_(1,3)` [`t_(1,3) = C = 2`]`=0 + 2``=2`
`E_4=Max{E_i + t_(i,4)} [i=1, 2, 3]`
`=Max{E_1 + t_(1,4); E_2 + t_(2,4); E_3 + t_(3,4)}`
`=Max{0 + 6; 3 + 5; 2 + 2}`
`=Max{6; 8; 4}`
`=8`
`E_5=Max{E_i + t_(i,5)} [i=2, 4]`
`=Max{E_2 + t_(2,5); E_4 + t_(4,5)}`
`=Max{3 + 7; 8 + 4}`
`=Max{10; 12}`
`=12`
Backward Pass Method
Backward Pass Method
`L_5=E_5=12`
`L_4=L_5 - t_(4,5)` [`t_(4,5) = G = 4`]`=12 - 4``=8`
`L_3=L_4 - t_(3,4)` [`t_(3,4) = E = 2`]`=8 - 2``=6`
`L_2=text{Min}{L_j - t_(2,j)} [j=5, 4]`
`=text{Min}{L_5 - t_(2,5); L_4 - t_(2,4)}`
`=text{Min}{12 - 7; 8 - 5}`
`=text{Min}{5; 3}`
`=3`
`L_1=text{Min}{L_j - t_(1,j)} [j=4, 3, 2]`
`=text{Min}{L_4 - t_(1,4); L_3 - t_(1,3); L_2 - t_(1,2)}`
`=text{Min}{8 - 6; 6 - 2; 3 - 3}`
`=text{Min}{2; 4; 0}`
`=0`
(b) The critical path in the network diagram has been shown. This has been done by double lines by joining all those events where E-values and L-values are equal.
The critical path of the project is : `1-2-4-5` and critical activities are `A,D,G`
The total project time is 12
The network diagram for the project, along with E-values and L-values, is
| | | | | |
| | | | | |
| | 3 `E_(3)=2` `L_(3)=6` | | D(5) `D : 2->4` |
| | | |
| | | D(5) `D : 2->4` | | E(2) `E : 3->4` |
| | | |
| | | | | |
Total cost = Direct normal cost + Indirect cost for 12 weeks
`=713+1xx30+250=993`
To begin crash analysis, the crash cost slope values for critical activities is
| Critical activity | Crash cost per week (Rs) |
| A (0 - 1) | `xx` (Crashed) |
| D (1 - 3) | `(250-150)/(5-3)=50` |
| G (3 - 4) | `(240-100)/(4-2)=70` |
The critical activity D with cost slope of Rs 50 per week, is the least expensive and can be crashed by 2 weeks
E-values and L-values for next crashed network
Forward Pass Method
Forward Pass Method
`E_1=0`
`E_2=E_1 + t_(1,2)` [`t_(1,2) = A = 3`]`=0 + 3``=3`
`E_3=E_1 + t_(1,3)` [`t_(1,3) = C = 2`]`=0 + 2``=2`
`E_4=Max{E_i + t_(i,4)} [i=1, 2, 3]`
`=Max{E_1 + t_(1,4); E_2 + t_(2,4); E_3 + t_(3,4)}`
`=Max{0 + 6; 3 + 3; 2 + 2}`
`=Max{6; 6; 4}`
`=6`
`E_5=Max{E_i + t_(i,5)} [i=2, 4]`
`=Max{E_2 + t_(2,5); E_4 + t_(4,5)}`
`=Max{3 + 7; 6 + 4}`
`=Max{10; 10}`
`=10`
Backward Pass Method
Backward Pass Method
`L_5=E_5=10`
`L_4=L_5 - t_(4,5)` [`t_(4,5) = G = 4`]`=10 - 4``=6`
`L_3=L_4 - t_(3,4)` [`t_(3,4) = E = 2`]`=6 - 2``=4`
`L_2=text{Min}{L_j - t_(2,j)} [j=5, 4]`
`=text{Min}{L_5 - t_(2,5); L_4 - t_(2,4)}`
`=text{Min}{10 - 7; 6 - 3}`
`=text{Min}{3; 3}`
`=3`
`L_1=text{Min}{L_j - t_(1,j)} [j=4, 3, 2]`
`=text{Min}{L_4 - t_(1,4); L_3 - t_(1,3); L_2 - t_(1,2)}`
`=text{Min}{6 - 6; 4 - 2; 3 - 3}`
`=text{Min}{0; 2; 0}`
`=0`
(b) The critical path in the network diagram has been shown. This has been done by double lines by joining all those events where E-values and L-values are equal.
The critical path of the project are :
(1) `1-2-4-5` and critical activities : `A,D,G`
(2) `1-2-5` and critical activities : `A,F`
(3) `1-4-5` and critical activities : `B,G`
The total project time is 10
The network diagram for the project, along with E-values and L-values, is
| | | | | |
| | | | | |
| | 3 `E_(3)=2` `L_(3)=4` | | D(3) `D : 2->4` |
| | | |
| | | D(3) `D : 2->4` | | E(2) `E : 3->4` |
| | | |
| | | | | |
Total cost = Direct normal cost + Indirect cost for 10 weeks
`=713+1xx30+2xx50+100=943`
The crashing activity `G` in the path `1-2-4-5` `(A,D,G)`, activity `F` in the path `1-2-5` `(A,F)`, each by 2 week
E-values and L-values for next crashed network
Forward Pass Method
Forward Pass Method
`E_1=0`
`E_2=E_1 + t_(1,2)` [`t_(1,2) = A = 3`]`=0 + 3``=3`
`E_3=E_1 + t_(1,3)` [`t_(1,3) = C = 2`]`=0 + 2``=2`
`E_4=Max{E_i + t_(i,4)} [i=1, 2, 3]`
`=Max{E_1 + t_(1,4); E_2 + t_(2,4); E_3 + t_(3,4)}`
`=Max{0 + 6; 3 + 3; 2 + 2}`
`=Max{6; 6; 4}`
`=6`
`E_5=Max{E_i + t_(i,5)} [i=2, 4]`
`=Max{E_2 + t_(2,5); E_4 + t_(4,5)}`
`=Max{3 + 5; 6 + 2}`
`=Max{8; 8}`
`=8`
Backward Pass Method
Backward Pass Method
`L_5=E_5=8`
`L_4=L_5 - t_(4,5)` [`t_(4,5) = G = 2`]`=8 - 2``=6`
`L_3=L_4 - t_(3,4)` [`t_(3,4) = E = 2`]`=6 - 2``=4`
`L_2=text{Min}{L_j - t_(2,j)} [j=5, 4]`
`=text{Min}{L_5 - t_(2,5); L_4 - t_(2,4)}`
`=text{Min}{8 - 5; 6 - 3}`
`=text{Min}{3; 3}`
`=3`
`L_1=text{Min}{L_j - t_(1,j)} [j=4, 3, 2]`
`=text{Min}{L_4 - t_(1,4); L_3 - t_(1,3); L_2 - t_(1,2)}`
`=text{Min}{6 - 6; 4 - 2; 3 - 3}`
`=text{Min}{0; 2; 0}`
`=0`
(b) The critical path in the network diagram has been shown. This has been done by double lines by joining all those events where E-values and L-values are equal.
The critical path of the project are :
(1) `1-2-4-5` and critical activities : `A,D,G`
(2) `1-2-5` and critical activities : `A,F`
(3) `1-4-5` and critical activities : `B,G`
The total project time is 8
The network diagram for the project, along with E-values and L-values, is
| | | | | |
| | | | | |
| | 3 `E_(3)=2` `L_(3)=4` | | D(3) `D : 2->4` |
| | | |
| | | D(3) `D : 2->4` | | E(2) `E : 3->4` |
| | | |
| | | | | |
Total cost = Direct normal cost + Indirect cost for 8 weeks
`=713+1xx30+2xx50+2xx70+2xx30+50=1093`
Since total project cost for 8 weeks is more than the cost for 10 weeks. So further crashing is not desirable.
Hence, project optimum time is 10 weeks and cost is 943.
Crashing schedule of project
| Project duration | Crashing activity and time | Direct Normal Cost | Direct Crashing Cost | Total (Normal + Crashing) | Indirect Cost | Total Cost |
| 13 | | 713 | `` | 713 | `400` | 1113 |
| 12 | A=1 | 713 | `1xx30=30` | 743 | `250` | 993 |
| 10 | D=2 | 713 | `1xx30+2xx50=130` | 843 | `100` | 943 |
| 8 | G;F=2 | 713 | `1xx30+2xx50+2xx70+2xx30=330` | 1043 | `50` | 1093 |
This material is intended as a summary. Use your textbook for detail explanation.
Any bug, improvement, feedback then