2. Network diagram : Activity i-j example ( Enter your problem )
  1. Example-1
Other related methods
  1. Network diagram : Activity, Predecessors
  2. Network diagram : Activity i-j
  3. Network diagram : Activity i-j, Name of Activity
  4. Critical path, Total float, Free float, Independent float : Activity, Predecessors, Duration
  5. Critical path, Total float, Free float, Independent float : Activity i-j, Duration
  6. Critical path, Total float, Free float, Independent float : Activity i-j, Name of Activity, Duration
  7. Project scheduling : Activity, Predecessors, to, tm, tp
  8. Project scheduling : Activity i-j, to, tm, tp
  9. Project scheduling : Activity i-j, Name of Activity, to, tm, tp
  10. Project crashing : Activity, Predecessors, Normal Time & Cost, Crash Time & Cost and Indirect Cost
  11. Project crashing : Activity i-j, Normal Time & Cost, Crash Time & Cost and Indirect Cost
  12. Project crashing : Activity i-j, Name of Activity, Normal Time & Cost, Crash Time & Cost and Indirect Cost
  13. Project crashing : Activity, Predecessors, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost
  14. Project crashing : Activity i-j, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost
  15. Project crashing : Activity i-j, Name of Activity, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost

1. Network diagram : Activity, Predecessors
(Previous method)
3. Network diagram : Activity i-j, Name of Activity
(Next method)

1. Example-1





Draw Network diagram
1-2
2-3
2-4
3-4
3-6
4-5
5-6
6-7
7-8


Solution:
The given problem is
Activity
1-2
2-3
2-4
3-4
3-6
4-5
5-6
6-7
7-8


Edge and it's preceded and succeeded node
EdgeNode1 `->` Node2
A01`->`2
A12`->`3
A22`->`4
A33`->`4
A43`->`6
A54`->`5
A65`->`6
A76`->`7
A87`->`8



The network diagram for the project is
A1
3
A4
6
A7
7
A8
8
1
A0
2
A3
A6
A2
4
A5
5

(Note: Same diagram as above. Move node position by dragging node.
If you are not able to select node then just click here for )
not supported





This material is intended as a summary. Use your textbook for detail explanation.
Any bug, improvement, feedback then Submit Here



1. Network diagram : Activity, Predecessors
(Previous method)
3. Network diagram : Activity i-j, Name of Activity
(Next method)





Share this solution or page with your friends.
 
 
Copyright © 2025. All rights reserved. Terms, Privacy
 
 

.