15. Project crashing : Activity i-j, Name of Activity, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost example
( Enter your problem )
|
- Example-1
|
Other related methods
- Network diagram : Activity, Predecessors
- Network diagram : Activity i-j
- Network diagram : Activity i-j, Name of Activity
- Critical path, Total float, Free float, Independent float : Activity, Predecessors, Duration
- Critical path, Total float, Free float, Independent float : Activity i-j, Duration
- Critical path, Total float, Free float, Independent float : Activity i-j, Name of Activity, Duration
- Project scheduling : Activity, Predecessors, to, tm, tp
- Project scheduling : Activity i-j, to, tm, tp
- Project scheduling : Activity i-j, Name of Activity, to, tm, tp
- Project crashing : Activity, Predecessors, Normal Time & Cost, Crash Time & Cost and Indirect Cost
- Project crashing : Activity i-j, Normal Time & Cost, Crash Time & Cost and Indirect Cost
- Project crashing : Activity i-j, Name of Activity, Normal Time & Cost, Crash Time & Cost and Indirect Cost
- Project crashing : Activity, Predecessors, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost
- Project crashing : Activity i-j, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost
- Project crashing : Activity i-j, Name of Activity, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost
|
|
1. Example-1
1. Project crashing to solve Time-Cost Trade-Off with varying Indirect cost
1-2 | A | 4 | 60 | 3 | 90 | 1-4 | B | 6 | 150 | 4 | 250 | 1-3 | C | 2 | 38 | 1 | 60 | 2-4 | D | 5 | 150 | 3 | 250 | 3-4 | E | 2 | 100 | 2 | 100 | 2-5 | F | 7 | 115 | 5 | 175 | 4-5 | G | 4 | 100 | 2 | 240 |
Varying Indirect cost Month = 15,14,13,12,11,10,9,8,7,6 Cost = 600,500,400,250,175,100,75,50,35,25
Solution: The given problem is
Activity | Name | Normal Time | Normal Cost | Crash Time | Crash Cost | 1-2 | A | 4 | 60 | 3 | 90 | 1-4 | B | 6 | 150 | 4 | 250 | 1-3 | C | 2 | 38 | 1 | 60 | 2-4 | D | 5 | 150 | 3 | 250 | 3-4 | E | 2 | 100 | 2 | 100 | 2-5 | F | 7 | 115 | 5 | 175 | 4-5 | G | 4 | 100 | 2 | 240 |
Edge and it's preceded and succeeded node
Edge | Node1 `->` Node2 | A | 1`->`2 | C | 1`->`3 | B | 1`->`4 | D | 2`->`4 | F | 2`->`5 | E | 3`->`4 | G | 4`->`5 |
The network diagram for the project, along with activity time, is
| | | | | | | | | | | | | | | | | | | | D(5) `D : 2->4` | E(2) `E : 3->4` |
| | | | | | | | | |
Forward Pass Method Forward Pass Method `E_1=0`
`E_2=E_1 + t_(1,2)` [`t_(1,2) = A = 4`]`=0 + 4``=4`
`E_3=E_1 + t_(1,3)` [`t_(1,3) = C = 2`]`=0 + 2``=2`
`E_4=Max{E_i + t_(i,4)} [i=1, 2, 3]`
`=Max{E_1 + t_(1,4); E_2 + t_(2,4); E_3 + t_(3,4)}`
`=Max{0 + 6; 4 + 5; 2 + 2}`
`=Max{6; 9; 4}`
`=9`
`E_5=Max{E_i + t_(i,5)} [i=2, 4]`
`=Max{E_2 + t_(2,5); E_4 + t_(4,5)}`
`=Max{4 + 7; 9 + 4}`
`=Max{11; 13}`
`=13`
Backward Pass Method Backward Pass Method `L_5=E_5=13`
`L_4=L_5 - t_(4,5)` [`t_(4,5) = G = 4`]`=13 - 4``=9`
`L_3=L_4 - t_(3,4)` [`t_(3,4) = E = 2`]`=9 - 2``=7`
`L_2=text{Min}{L_j - t_(2,j)} [j=5, 4]`
`=text{Min}{L_5 - t_(2,5); L_4 - t_(2,4)}`
`=text{Min}{13 - 7; 9 - 5}`
`=text{Min}{6; 4}`
`=4`
`L_1=text{Min}{L_j - t_(1,j)} [j=4, 3, 2]`
`=text{Min}{L_4 - t_(1,4); L_3 - t_(1,3); L_2 - t_(1,2)}`
`=text{Min}{9 - 6; 7 - 2; 4 - 4}`
`=text{Min}{3; 5; 0}`
`=0`
(b) The critical path in the network diagram has been shown. This has been done by double lines by joining all those events where E-values and L-values are equal. The critical path of the project is : `1-2-4-5` and critical activities are `A,D,G`
The total project time is 13 The network diagram for the project, along with E-values and L-values, is
| | | | | | | | | | | | | | 3 `E_(3)=2` `L_(3)=7` | D(5) `D : 2->4` |
| | | | | | D(5) `D : 2->4` | E(2) `E : 3->4` |
| | | | | | | | | |
Critical activity | Crash cost per week (Rs) | A (1 - 2) | `(90-60)/(4-3)=30` | C (1 - 3) | `(60-38)/(2-1)=22` | B (1 - 4) | `(250-150)/(6-4)=50` | D (2 - 4) | `(250-150)/(5-3)=50` | F (2 - 5) | `(175-115)/(7-5)=30` | E (3 - 4) | - | G (4 - 5) | `(240-100)/(4-2)=70` |
Total cost = Direct normal cost + Indirect cost for 13 weeks `=713+400=1113`
To begin crash analysis, the crash cost slope values for critical activities is
Critical activity | Crash cost per week (Rs) | A (0 - 1) | `(90-60)/(4-3)=30` | D (1 - 3) | `(250-150)/(5-3)=50` | G (3 - 4) | `(240-100)/(4-2)=70` |
The critical activity A with cost slope of Rs 30 per week, is the least expensive and can be crashed by 1 weeks
E-values and L-values for next crashed network
Forward Pass Method Forward Pass Method `E_1=0`
`E_2=E_1 + t_(1,2)` [`t_(1,2) = A = 3`]`=0 + 3``=3`
`E_3=E_1 + t_(1,3)` [`t_(1,3) = C = 2`]`=0 + 2``=2`
`E_4=Max{E_i + t_(i,4)} [i=1, 2, 3]`
`=Max{E_1 + t_(1,4); E_2 + t_(2,4); E_3 + t_(3,4)}`
`=Max{0 + 6; 3 + 5; 2 + 2}`
`=Max{6; 8; 4}`
`=8`
`E_5=Max{E_i + t_(i,5)} [i=2, 4]`
`=Max{E_2 + t_(2,5); E_4 + t_(4,5)}`
`=Max{3 + 7; 8 + 4}`
`=Max{10; 12}`
`=12`
Backward Pass Method Backward Pass Method `L_5=E_5=12`
`L_4=L_5 - t_(4,5)` [`t_(4,5) = G = 4`]`=12 - 4``=8`
`L_3=L_4 - t_(3,4)` [`t_(3,4) = E = 2`]`=8 - 2``=6`
`L_2=text{Min}{L_j - t_(2,j)} [j=5, 4]`
`=text{Min}{L_5 - t_(2,5); L_4 - t_(2,4)}`
`=text{Min}{12 - 7; 8 - 5}`
`=text{Min}{5; 3}`
`=3`
`L_1=text{Min}{L_j - t_(1,j)} [j=4, 3, 2]`
`=text{Min}{L_4 - t_(1,4); L_3 - t_(1,3); L_2 - t_(1,2)}`
`=text{Min}{8 - 6; 6 - 2; 3 - 3}`
`=text{Min}{2; 4; 0}`
`=0`
(b) The critical path in the network diagram has been shown. This has been done by double lines by joining all those events where E-values and L-values are equal. The critical path of the project is : `1-2-4-5` and critical activities are `A,D,G`
The total project time is 12 The network diagram for the project, along with E-values and L-values, is
| | | | | | | | | | | | | | 3 `E_(3)=2` `L_(3)=6` | D(5) `D : 2->4` |
| | | | | | D(5) `D : 2->4` | E(2) `E : 3->4` |
| | | | | | | | | |
Total cost = Direct normal cost + Indirect cost for 12 weeks `=713+1xx30+250=993`
To begin crash analysis, the crash cost slope values for critical activities is
Critical activity | Crash cost per week (Rs) | A (0 - 1) | `xx` (Crashed) | D (1 - 3) | `(250-150)/(5-3)=50` | G (3 - 4) | `(240-100)/(4-2)=70` |
The critical activity D with cost slope of Rs 50 per week, is the least expensive and can be crashed by 2 weeks
E-values and L-values for next crashed network
Forward Pass Method Forward Pass Method `E_1=0`
`E_2=E_1 + t_(1,2)` [`t_(1,2) = A = 3`]`=0 + 3``=3`
`E_3=E_1 + t_(1,3)` [`t_(1,3) = C = 2`]`=0 + 2``=2`
`E_4=Max{E_i + t_(i,4)} [i=1, 2, 3]`
`=Max{E_1 + t_(1,4); E_2 + t_(2,4); E_3 + t_(3,4)}`
`=Max{0 + 6; 3 + 3; 2 + 2}`
`=Max{6; 6; 4}`
`=6`
`E_5=Max{E_i + t_(i,5)} [i=2, 4]`
`=Max{E_2 + t_(2,5); E_4 + t_(4,5)}`
`=Max{3 + 7; 6 + 4}`
`=Max{10; 10}`
`=10`
Backward Pass Method Backward Pass Method `L_5=E_5=10`
`L_4=L_5 - t_(4,5)` [`t_(4,5) = G = 4`]`=10 - 4``=6`
`L_3=L_4 - t_(3,4)` [`t_(3,4) = E = 2`]`=6 - 2``=4`
`L_2=text{Min}{L_j - t_(2,j)} [j=5, 4]`
`=text{Min}{L_5 - t_(2,5); L_4 - t_(2,4)}`
`=text{Min}{10 - 7; 6 - 3}`
`=text{Min}{3; 3}`
`=3`
`L_1=text{Min}{L_j - t_(1,j)} [j=4, 3, 2]`
`=text{Min}{L_4 - t_(1,4); L_3 - t_(1,3); L_2 - t_(1,2)}`
`=text{Min}{6 - 6; 4 - 2; 3 - 3}`
`=text{Min}{0; 2; 0}`
`=0`
(b) The critical path in the network diagram has been shown. This has been done by double lines by joining all those events where E-values and L-values are equal. The critical path of the project are : (1) `1-2-4-5` and critical activities : `A,D,G`
(2) `1-2-5` and critical activities : `A,F`
(3) `1-4-5` and critical activities : `B,G`
The total project time is 10 The network diagram for the project, along with E-values and L-values, is
| | | | | | | | | | | | | | 3 `E_(3)=2` `L_(3)=4` | D(3) `D : 2->4` |
| | | | | | D(3) `D : 2->4` | E(2) `E : 3->4` |
| | | | | | | | | |
Total cost = Direct normal cost + Indirect cost for 10 weeks `=713+1xx30+2xx50+100=943`
The crashing activity `G` in the path `1-2-4-5` `(A,D,G)`, activity `F` in the path `1-2-5` `(A,F)`, each by 2 week
E-values and L-values for next crashed network
Forward Pass Method Forward Pass Method `E_1=0`
`E_2=E_1 + t_(1,2)` [`t_(1,2) = A = 3`]`=0 + 3``=3`
`E_3=E_1 + t_(1,3)` [`t_(1,3) = C = 2`]`=0 + 2``=2`
`E_4=Max{E_i + t_(i,4)} [i=1, 2, 3]`
`=Max{E_1 + t_(1,4); E_2 + t_(2,4); E_3 + t_(3,4)}`
`=Max{0 + 6; 3 + 3; 2 + 2}`
`=Max{6; 6; 4}`
`=6`
`E_5=Max{E_i + t_(i,5)} [i=2, 4]`
`=Max{E_2 + t_(2,5); E_4 + t_(4,5)}`
`=Max{3 + 5; 6 + 2}`
`=Max{8; 8}`
`=8`
Backward Pass Method Backward Pass Method `L_5=E_5=8`
`L_4=L_5 - t_(4,5)` [`t_(4,5) = G = 2`]`=8 - 2``=6`
`L_3=L_4 - t_(3,4)` [`t_(3,4) = E = 2`]`=6 - 2``=4`
`L_2=text{Min}{L_j - t_(2,j)} [j=5, 4]`
`=text{Min}{L_5 - t_(2,5); L_4 - t_(2,4)}`
`=text{Min}{8 - 5; 6 - 3}`
`=text{Min}{3; 3}`
`=3`
`L_1=text{Min}{L_j - t_(1,j)} [j=4, 3, 2]`
`=text{Min}{L_4 - t_(1,4); L_3 - t_(1,3); L_2 - t_(1,2)}`
`=text{Min}{6 - 6; 4 - 2; 3 - 3}`
`=text{Min}{0; 2; 0}`
`=0`
(b) The critical path in the network diagram has been shown. This has been done by double lines by joining all those events where E-values and L-values are equal. The critical path of the project are : (1) `1-2-4-5` and critical activities : `A,D,G`
(2) `1-2-5` and critical activities : `A,F`
(3) `1-4-5` and critical activities : `B,G`
The total project time is 8 The network diagram for the project, along with E-values and L-values, is
| | | | | | | | | | | | | | 3 `E_(3)=2` `L_(3)=4` | D(3) `D : 2->4` |
| | | | | | D(3) `D : 2->4` | E(2) `E : 3->4` |
| | | | | | | | | |
Total cost = Direct normal cost + Indirect cost for 8 weeks `=713+1xx30+2xx50+2xx70+2xx30+50=1093`
Since total project cost for 8 weeks is more than the cost for 10 weeks. So further crashing is not desirable. Hence, project optimum time is 10 weeks and cost is 943.
Crashing schedule of project
Project duration | Crashing activity and time | Direct Normal Cost | Direct Crashing Cost | Total (Normal + Crashing) | Indirect Cost | Total Cost | 13 | | 713 | `` | 713 | `400` | 1113 | 12 | A=1 | 713 | `1xx30=30` | 743 | `250` | 993 | 10 | D=2 | 713 | `1xx30+2xx50=130` | 843 | `100` | 943 | 8 | G;F=2 | 713 | `1xx30+2xx50+2xx70+2xx30=330` | 1043 | `50` | 1093 |