Home > Operation Research calculators > PERT and CPM example

7. Project scheduling : Activity, Predecessors, to, tm, tp example ( Enter your problem )
  1. Example-1
Other related methods
  1. Network diagram : Activity, Predecessors
  2. Network diagram : Activity i-j
  3. Network diagram : Activity i-j, Name of Activity
  4. Critical path, Total float, Free float, Independent float : Activity, Predecessors, Duration
  5. Critical path, Total float, Free float, Independent float : Activity i-j, Duration
  6. Critical path, Total float, Free float, Independent float : Activity i-j, Name of Activity, Duration
  7. Project scheduling : Activity, Predecessors, to, tm, tp
  8. Project scheduling : Activity i-j, to, tm, tp
  9. Project scheduling : Activity i-j, Name of Activity, to, tm, tp
  10. Project crashing : Activity, Predecessors, Normal Time & Cost, Crash Time & Cost and Indirect Cost
  11. Project crashing : Activity i-j, Normal Time & Cost, Crash Time & Cost and Indirect Cost
  12. Project crashing : Activity i-j, Name of Activity, Normal Time & Cost, Crash Time & Cost and Indirect Cost
  13. Project crashing : Activity, Predecessors, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost
  14. Project crashing : Activity i-j, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost
  15. Project crashing : Activity i-j, Name of Activity, Normal Time & Cost, Crash Time & Cost and varying Indirect Cost

6. Critical path, Total float, Free float, Independent float : Activity i-j, Name of Activity, Duration
(Previous method)
8. Project scheduling : Activity i-j, to, tm, tp
(Next method)

1. Example-1





Project scheduling with uncertain activity times (Optimistic, Most likely, Pessimistic)
A-117
B-147
C-228
DA111
EB2514
FC258
GD,E3615


Solution:
Expected time of each activity,
Activity`t_o``t_m``t_p``t_e=(t_o + 4*t_m + t_p)/6``sigma^2=((t_p - t_o)/6)^2`
A11721
B14741
C22831
D11110
E251464
F25851
G361574



The earliest and latest expected time for each activity is calculated by considering the expected time `t_e`

ActivityImmediate PredecessorsDuration
A-2
B-4
C-3
DA1
EB6
FC5
GD,E7


Edge and it's preceded and succeeded node
EdgeNode1 `->` Node2
A1`->`2
B1`->`3
C1`->`4
D2`->`5
E3`->`5
F4`->`6
G5`->`6



The network diagram for the project, along with activity time, is
2
A(2)
D(1)
E(6)
5
1
B(4)
3
G(7)
C(3)
G(7)
4
F(5)
6

(Note: Same diagram as above. Move node position by dragging node.
If you are not able to select node then just click here for )
not supported


Forward Pass Method

`E_1=0`

`E_2=E_1 + t_(1,2)``=0 + 2``=2`

`E_3=E_1 + t_(1,3)``=0 + 4``=4`

`E_4=E_1 + t_(1,4)``=0 + 3``=3`

`E_5=Max{E_i + t_(i,5)} [i=2, 3]`

`=Max{E_2 + t_(2,5); E_3 + t_(3,5)}`

`=Max{2 + 1; 4 + 6}`

`=Max{3; 10}`

`=10`

`E_6=Max{E_i + t_(i,6)} [i=4, 5]`

`=Max{E_4 + t_(4,6); E_5 + t_(5,6)}`

`=Max{3 + 5; 10 + 7}`

`=Max{8; 17}`

`=17`


Backward Pass Method

`L_6=E_6=17`

`L_5=L_6 - t_(5,6)``=17 - 7``=10`

`L_4=L_6 - t_(4,6)``=17 - 5``=12`

`L_3=L_5 - t_(3,5)``=10 - 6``=4`

`L_2=L_5 - t_(2,5)``=10 - 1``=9`

`L_1=text{Min}{L_j - t_(1,j)} [j=2, 3, 4]`

`=text{Min}{L_2 - t_(1,2); L_3 - t_(1,3); L_4 - t_(1,4)}`

`=text{Min}{9 - 2; 4 - 4; 12 - 3}`

`=text{Min}{7; 0; 9}`

`=0`


(b) The critical path in the network diagram has been shown. This has been done by red lines by joining all those events where E-values and L-values are equal.
The critical path of the project is : `1-3-5-6` and critical activities are `B,E,G`

The total project time is 17
The network diagram for the project, along with E-values and L-values, is
2
`E_(5)=10`
`L_(5)=10`
A(2)
`E_(2)=2`
`L_(2)=9`
D(1)
E(6)
5
1
B(4)
3
G(7)
`E_(1)=0`
`L_(1)=0`
C(3)
`E_(3)=4`
`L_(3)=4`
G(7)
`E_(4)=3`
`L_(4)=12`
4
F(5)
6
`E_(6)=17`
`L_(6)=17`


(Note: Same diagram as above. Move node position by dragging node.
If you are not able to select node then just click here for )
not supported





This material is intended as a summary. Use your textbook for detail explanation.
Any bug, improvement, feedback then Submit Here



6. Critical path, Total float, Free float, Independent float : Activity i-j, Name of Activity, Duration
(Previous method)
8. Project scheduling : Activity i-j, to, tm, tp
(Next method)





Share this solution or page with your friends.
 
 
Copyright © 2025. All rights reserved. Terms, Privacy
 
 

.